Construction of Rope ways

  • patna
  • 22-Jun-2018 - 31-Jul-2022

Schemes of Rope way

Approved amount

Updated status

Construction of new rope way in Rajgir

20.18 crores

  • Out of 6 tower, work of 4 tower has been completed.
  • This scheme is expected to be completed by June, 2018.

Construction of Rope way in Mandar Mountain, Banka

8.55 crores

  • Foundation work is under  process in 4 towers.
  • Work is expected to be completed by June, 2018.

Construction of Rope way in Rohtas Garh fort

12.65 crores

  • Wildlife clearance has been received for this work.
  • Approval need to be provided by Environment and forest Department on Land acquisition proposal.

Construction of Rope way in Vanavaar Mountain, Jehanabad and in Mundeshvari Mountain, Kaimur

 

  • Action is being taken to get certificate of FRA (Forest Rights Act) 2006 from District Magistrate of Jehanabad and Kaimur.

Construction of Ropeway in Dungeshvari Mountain, Gaya, Brahmnyoni Mountain, Gaya and in Pretshila Mountain, Gaya.

 

  • Forest and Wildlife clearance is in progress for all three projects.